We are delighted to have completed the installation of a new sprinkler system into this block of 9 apartments in Hackney which involved careful logistical organisation including each tenant moving out for 3 weeks whilst our team created access routes in the MF ceilings, installed all new sprinkler pipework, patched in the ceiling and then decorated before a thorough clean ready for them to move back in.

Client: IDM Properties

Surveyor: Anstey Horne

Value: Confidential

Programme: 6 x 3 weeks for 1 storey apartments and 3 x 4 weeks for the duplexes, all overlapping by one week – 15 weeks in total